人行棧橋預制拼裝技術方案研究
首發時間:2023-09-11
摘要:近年來隨著城市的進一步發展,人們生活水平提高,也開始更加關注健康出行和環境保護。目前海邊棧道橋梁建設大部門采用現澆的形式,占地面積較大,使得施工周期較長,成本也更高。為了進一步解決這個問題,保證片區慢行道路服務水平不降低,利用橋位用地建設,采用植樁結合預制疊合板方式施工慢行橋梁,以緩解施工過程緩慢、建設地塊小的問題,促進城市的健康發展,改善人居環境。本文較為詳細地介紹了植樁結合預制疊合板方式的慢行橋梁的特點,建設用地少,場地靈活布置,結構合理可靠,可預制拼裝,節約時間,綠色環保,先進的智能化控制設備,性價比高等,在城市發展中發揮有益作用,可推廣和復制,為市政工程發展提供新的思路和想法。
關鍵詞: 市政工程 人行棧橋 主體結構 預制 拼裝 方案研究
For information in English, please click here
Research on the Technical Scheme for Prefabrication and Assembly of Pedestrian Trestles
Abstract:In recent years, with the further development of cities and the improvement of people\'s living standards, people have also begun to pay more attention to healthy travel and environmental protection. At present, most of the construction of seaside trestle bridges adopts the cast-in-place form, which occupies a large area, resulting in a longer construction period and higher costs. In order to further solve this problem and ensure that the service level of slow moving roads in the area does not decrease, the construction of slow moving bridges using bridge site land is carried out by using pile planting combined with prefabricated composite plates to alleviate the problems of slow construction process and small construction land, promote the healthy development of the city, and improve the living environment. This article provides a detailed introduction to the characteristics of slow-moving bridges using the combination of pile planting and prefabricated composite plates. The construction land is small, the site is flexible and arranged, the structure is reasonable and reliable, can be prefabricated and assembled, saves time, is green and environmentally friendly, advanced intelligent control equipment, and has a high cost-effectiveness. It plays a beneficial role in urban development, can be promoted and replicated, and provides new ideas and ideas for the development of municipal engineering..
Keywords: Municipal engineering Pedestrian trestle Main structure Prefabrication Assembly Scheme research
基金:
引用
No.****
動態公開評議
共計0人參與
勘誤表
人行棧橋預制拼裝技術方案研究
評論
全部評論